Location
London
Client
Crossrail
Main Contractor
Costain Skanska JV
Value
£15m
Duration
124 Weeks
Project
Crossrail, Civils
Works consisted the construction of the capping beams to the perimeter of the site plus two shafts dropping five storeys using top down construction.
Much of the works were constructed on a 24/7 programme basis with the requirement to fluctuate the labour dramatically to suit the needs of the programme and availability of work. Works commenced later than expected but at the end of the original programme the project was completed on time on budget.