PROJECT SUMMARY

  • Location

    Bognor Regis

  • Client

    Barratt Homes

  • Main Contractor

    Hochtief Murphy JV

  • Value

    £2m

  • Duration

    52 Weeks

  • Project

    Highways, Civils

PROJECT DETAILS

This is the largest infastructure project for Kelly Formwork Civils to date. The structure once completed will span over 500m long providing a relief road for Bognor Regis that has been needed for over a decade.


Work comprised of the construction of numerous sets of radius columns beneath the water table to support large pre-cast cross beams. These beams were to support eleven span beam each weighing over 60T each and 30m in length.


All beams and crossheads were installed by Kelly Civils. The second phase of the works consist of reinforcement to the spanning beams to cast in-situ slabs in phases from one end of the structure to the other.


The radius columns were cast to a very high specification using specially fabricated steel column formers.