Kelly Formwork (UK) Ltd Awarded Next Phase of the Eastern Ticket Hall

22 - 01 - 2014

Kelly Formwork (UK) Ltd has been awarded the next phase of the Eastern Ticket Hall for Costain/ Skanska worth 10 Million secured after successfully completing the Western Ticket Hall 1 month ahead of program.

This package entails construction of the Eastern Ticket Hall Main Station Reinforced Concrete sub and Superstructure, the Western Ticket Hall Superstructure together with the station platforms running between Davies Street and Hanover Square.

Top Down Construction is being employed together with two Slip Formed Vent Shafts and many precast elements. Works are programmed to be complete by December 2015.