OUR TESTIMONIALS

Gents,

I would like to thank you all for excellent work during yesterday’s pour and all the hard work leading up to it – I know it was not walk in the park. The successful execution of this pour wouldn’t happen without good planning, clear line of communication and reliable supply chain partners who performed as they promised.

This was our first large pour with many more to come and I am really glad it went so well. It is a big milestone for Section 4 – something to be proud of.

Please forward my thanks to everybody involved.

Regards,

Ondrej

Ondrej Humplik MEng CEng MICE

Construction Manager

 

Daryll,

We have had a sign off from the station that platforms 20, 21, 22 and concourse are officially ready for passenger trains. The station is not going to run trains today due to some internal issues but as far as we are concerned the project delivered on what we had to do. Although the job is not fully complete, this is a huge achievement for everyone involved. Thanks for all the hard work that Kelly Formwork have done over the last few months (especially the last few days). Please pass this onto Christian and the lads.

Special thanks for the additional hours put in yesterday to help us get over the line.

Regards, Stefan Sorani

                                                            

Daryll

On my site tour yesterday I came around the Kelly Briefing point that has clearly fenced off and branded ‘Kelly Land’.  I went inside the area and was very impressed with the clear ordered manner that the briefing area is organised and set out.  This is just a reflection of the high standards that I have become accustomed to when working with your business.  I wanted to just pass my thanks for setting the standard across the projects and will be getting the other contractors working on our projects to follow the Kelly lead.

Well done to you and your team

Derek Van Rensburg, Lead Delivery

Waterloo International Terminal

"As part of the Hammersmith Flyover Strengthening Works (Phase-2) Costain, as Principal Contractor employed Kelly Formwork to construct a mock-up of half a span of the flyover bridge which is to be used for a number of activities relative to the permanent works on the flyover.

This includes, confined space entry and rescue training, trials of works within the bridge as well as trials for the cantilevered section to the underside of the bridge. This half span was formed onto a false-work platform with one cell reinforced concrete, incorporating the cantilevered arch and the other cells formed with timber panelling, one of these also incorporated the cantilevered arch.

Led by their experienced Site Manager, the Kelly Formwork operatives worked tirelessly to complete the main installations within a tight 5 week programme, while keeping a positive attitude throughout. They have constructed this unusual and complex structure to a high standard of quality, while maintaining excellent compliance to the required health & Safety procedures on site"

Kind Regards

Brian Penny, Senior Engineer, Costain Ltd

Hammersmith Flyover

"Hi Daryll,

Just a quick e-mail to congratulate you and your team for the good job you have done in Plumstead Portal.

Roof slabs 3 to 26 (including all associated lining walls, spine walls, flood walls, etc) have been completed to very high quality standards, 3 weeks ahead of programme but most importantly with an excellent safety record."

Keep up the good work for roof slabs 1 and 2 over the next weeks"

Regards

Santiago Daniele, Construction Manager Portals, Hoctief Murphy

 

C310 Plumstead Portal

Dear Daryll,

Many Thanks for all your efforts in getting the project to 16th Dec.  You made a huge difference onsite, and I am personally convinced that this was one of the key reasons that yesterday’s success happened.

Well done again, and do pass on my thanks your team.

Kind Regards, Claire Carr, Project Manager, C411 & C412: Crossrail Bond Street Station Works

 

“Kelly Formwork have provided FRC support on our Bond Street Project. They have performed exceptionally well. The care and quality of the works has been excellent. Their proactive approach to Health and Safety has been very refreshing and has led to an outstanding safety record.

Daryll Kelly has been a very visible leader. His determination to perform well comes out in his workforce who are
motivated to succeed and receptive to innovation and ways to improve. 

I would recommend Kelly Formwork for the FRC works on CRL projects”

Regards, Lee Davies, Operations Director, Costain PLC

 

Bond Street C412 & C411

Our Profiles